Friday, April 28, 2006

Royal Brompton and Harefield Hospitals Plans for NHS Foundation Trust Status

The Royal Brompton and Harefield Hospital are working through the process of applying for Foundation Trust status within the NHS. More information on what this means can be found here:

http://www2.rbht.nhs.uk/foundation

The hospital is asking for interested people within the community to apply to become members of the Trust. This process and what it means are discussed on the website. Please take the time to read this as it could have a large impact on the Hospital and the wider village.

Thursday, April 27, 2006

Charity Football & Fun on Sunday

On Sunday 30th April, there is a fun day for Rion Barr, who died last year of a heart defect. There are notices throughout the village but there is a Football Match between the team Rion used to play for and the Veterans who were sponsored by the Rubber Company. It is at 4 p. m until 6 p.m. the match with face paining and other activities for children, with a raffle and auction lots of prizes donated from the village and special items include a Chelsea signed football, and two from Watford. It is being held at the Harefield Football Club and all proceeds will be given to the Specialist Heart Fund at the Hospital.

Refuse, Recycling & Garden Waste Collections for the May Bank Holidays 2006

The London Borough of Hillingdon have produced the following webiste which shows the changes to the rubbish collections during the Holiday periods:

http://www.hillingdon.gov.uk/environment/waste/bh06_recrefgdn.php

Friday, April 21, 2006

National Grid Harefield to Southall Gas Pipeline

At the meeting held in the Park Lane Village Centre on the evening of 20th April, we were given a very informative update presentation by National Grid on their plans for the new 19km-long 1220mm-diameter gas pipeline between Harefield and Southall. We would like to note our thanks to the team for taking the time to come and present to the Village on this major project that will have an impact on the area during 2007-2008. The Association will continue to work with National Grid and to monitor the plans for the pipeline. The following is a summary of the information that was presented:

Why?

The pipeline is needed to maintain gas supplies safely and reliably following significant increases in the demand for gas in the West London area.

When?

Construction of special engineering sections, such as major crossings under the A40 and the A312 will be carried out from April 2007. The majority of the pipeline will be constructed between April 2008 and October 2008. Construction during this period gives the best condition for working and restoration of the land.


How is the route decided?

The pipeline needs to be constructed between two particular points on the existing gas supply network -Harefield and Southall - to enable more gas to be supplied to West London.

Potential route corridors have been considered, in an area of 196 km square, based on:

1. The start and finish of the pipeline.
2. The reasonable avoidance of centres of population.
3. The reasonable avoidance of significant environmental features and sites of archaeological significance.
4. The reasonable avoidance of potentially difficult construction areas, such as steep slopes, peat and complex river crossings.
5. The shortest distance (taking into consideration points 1-4)

A map of the proposed route is available from National Grid (or Association Committee Members) - We have been asked not to post a copy onto this website.

Construction Methods:
The pipeline will be tunneled beneath roads, railway crossings and major watercourses. The remainder will be placed in a covered trench.

Working Hours:
For the main pipeline construction, from April 2008 - October 2009, planned working hours are 7am-7pm Monday to Friday and 7am-4pm on Saturdays - Sunday working may be necessary, but this will be kept to a minimum.
During tunnel construction, which is expected to start in April 2007, there will be periods when 24-hour working is necessary. Any construction activity above ground will be kept to a minimum outside of normal working hours.

Working Area:
One of the first activities is to mark out the centre line for the pipeline and then to peg out the working width (generally 44 meters). Pre-construction drainage is installed and topsoil is then carefully removed and stored within this working width.

Construction Progress:
Pipeline construction is carried out in a series of phases that will run concurrently along the length of the pipeline. These activities are as follows:

1. Lay out the pipeline above ground.
2. Weld the pipe above ground with breaks for road crossings etc. The welds are then tested to check for soundness and coated to provide additional protection.
3. Excavate a 2 meters-wide by 2.5 meters deep trench. It is normal practice to have this open for the minimum amount of time for safety and to reduce the likelihood of it being affected by adverse weather conditions.
4. Place the pipe in the trench.
5. Reinstate the land in the original layers that were removed - this includes the replacement of any hedges or similar landmarks that have to be removed during the construction process.

Summary:
It is the aim of National Grid to construct the pipeline with the minimum amount of inconvenience and to work with all those who may be affected to achieve this.

Care for the environment is a prime concern during the pipeline construction and we work very closely with environmentalists throughout the process. All land will be fully reinstated and the only permanent reminder of the pipeline will be its marker posts. National Grid maintains responsibility for returning the land to its original condition.

For further information please contact:

National Grid Community Relations Team 0800 731 1231

You may also contact any members of the Committee with any questions and feedback on this project.

New Village Policeman

We have to welcome our new Police Constable to the village - he is PC Rob Woolf who should soon be a familiar figure around our streets. He joins us from one of the Police Quick Response Teams and is looking forward to meeting more of the local people.

If there is a problem he can be contacted on the following numbers:

Office: 01895 822622 (has an answerphone)
Mobile: 07909 665831 -- he suggests that even if you phone 999 to report a problem, try giving him a call on this number as he may be able to get to you sooner if he is in the Village (once in fast response - always a fast responsder!!)

PC Woolf will be attending the next meeting of the Tenants and Residents in May and will be happy to take your questions.

Tuesday, April 04, 2006

Ronnie Doyle's Leaving Do!!

Our local Police Constable Ronnie Doyle is leaving the village next week. To show our appreciation for the work she has done there is a leaving do at the Harefield Cricket Club in Breakspear Road, this Friday (6th April) at 6:00pm.